Modernization of st. #1 turbogenerator. Replacement of the electromagnetic exciter with a thyristor excitation system (LLC “Kremenchuk TEC”)

Years of implementation

 

2016-2018
Type of works

Modification of the design and estimate documentation, installation work, equipment supply, commissioning works

Equipment used; specifics of works provided

Project development, installation, complex tests and commissioning of the excitation system based on a power transformer type TSZP-1250/6-U3 6.3/665V (PE "ELTIZ") and thyristor excitation system type SVTG-1,3k/350-1ES2T2,5-UHL4 (LLC "RDE "PREOBRAZOVATEL-COMPLEX")

Photo

Replacement of the existing single-channel thyristor self-excitation system type STS-300-2000-2,5-UHL4 TG-3 with a microprocessor controlled two-channel excitation system type SSTE-2000-300-2,5-UHL4 (LLC Firm “Tech-Nova” (Chernihiv TEC))

Years of implementation

 

2017-2018
Type of works

Design, installation works, equipment supply, software development, complex tests and commissioning works

Equipment used; specifics of works provided

The excitation system STS-300-2000-2,5-UHL4 is a Ukrainian development (RE LLC "PREOBRAZOVATELNAYA TEHNIKA"). The system implements HMI Weintek based AWP. Climatization of the room with the equipment of the excitation system was carried out by column air conditioner MIDEA MFM-48. As part of complex tests and commissioning, thermal imaging surveys of power thyristor sections were carried out

Photo

Replacement of the electromagnetic exciter of the turbine generator TV-60-2 and ARZ type POA with a single-group two-channel thyristor self-excitation system implementing redundancy schemes (1+1) with microprocessor-based ARV and AWP for monitoring (Ltd. “Euro-Rekonstruktsia” (Darnytsia TEC), Kyiv), turbine generators TG-5, TG-6, TG-7

Years of implementation2017-2021
Type of works

Design, installation works, equipment supply, software development, complex tests and commissioning works

Equipment used; specifics of works provided

The works starting with dismantling the old system finishing with grid connection to the Ukrainian power system with 60 MW output for TG-5 took 41 days, including dismantling, installation, connection of power and control circuits, as well as comprehensive testing and commissioning. The excitation system SSTE-800-250-2.5-UHL4 (SPE "PREOFRESHCHATELNAYA TECHNIKA") is a Ukrainian development, the field damping system is developed under a Ukrainian patent. The power transformer TSZP-630/10-UZ (PE "ELTIZ") 630 kVA, 10.5 kV/0.475 kV, U/D-11 and the microprocessor-based relay protection device RZL-01 (LLC "SPE "RELSIS") are also developed by Ukrainian companies. The premises with the excitation system equipment were air-conditioned by MIDEA MFM-48 column air conditioners. As part of the comprehensive testing and commissioning, thermal imaging surveys of the power thyristor sections and process oscillography were performed using the ADC-BS-8V-9C digital recorder of electrical parameters. Digital models of the turbine generator were used to develop the field damping system and to adjust the current, voltage, and reactive power controllers

Photo

Replacement of thyristor exciters OVD-2, OVD-4, DZF (Ferrexpo Poltava Mining)

Years of implementation2018-2019
Type of works

Design, equipment supply, construction and installation works, complex commissioning and testing

Equipment used; specifics of works provided performance

Thyristor exciter VTE-320/230-1T20-0002-UHL4 (SPE "PREOBRAZOVATEL-KOMPLEX" LLC). During the adjustment of the exciter's ARF regulators, we used process oscillography with the ADC-BS-8V-9C digital recorder of electrical parameters

Photo

Technical re-equipment of the st. #. 1 excitation system G-1 TVV-320 (thermal power plant (TPP) TEC-6, “Kyivski TEC”, Municipal Enterprise "Kyivteploenergo")

Years of implementation2019-2022
Type of works

Design work, equipment supply. The implementation of the project has been suspended due to military operations on the territory of Ukraine

Equipment used; specifics of works provided

Designing the replacement of the 320 MW TG excitation system with a static thyristor self-excitation system SVTG-3.2k/500-1 KS2T2.5-AR24-UHL4 (SPE "PREOBRAZOVATEL-KOMPLEX" LLC) with nonlinear damping resistors Metrosil FME/8000/600A/US12P/4PP/2SS, which works in conjunction with the Emerson Ovation ATS. Replacement of the unit's RPA with ATS terminals (RET670, REG670 and others), replacement of the generator circuit breaker with a 20kV, 13.3kA FKG1F (ALSTOM) circuit breaker with a 120kA breaking capacity, replacement of the synchronizer with a SYNCHROTACT 6 SYN6201 ATS, complex automation, inspection of building structures, architectural and construction part (strengthening of supporting structures for installation of power transformer TSZP-4130/20-U3 (PE "ELTIZ") weighing 11.6 tons. ), heating and ventilation (use of precision air conditioners to cool down the transformer room). Within the framework of the project, dynamic stability calculations were implemented in accordance with the requirements of SOU-N IEC 40.1-00100227-68 2012 "Power System Sustainability. Guidelines" (models of the ST4C thyristor self-excitation regulator and the PSS2B system stabilizer in accordance with the requirements of IEEE 421.5 Recommended Practice for Excitation System Models for Power System Stability Studies)

Photo

Slavyanska TPP. Reconstruction of power unit No. 7 with a capacity of 800 MW. Reconstruction of the control system to bring it in line with ENTSO-E requirements (reconstruction of the generator excitation system)

Years of implementation2019-2022
Type of works

Project work

Equipment used; specifics of works provided

Design work and selection of equipment for the most powerful thermal generation machine in Ukraine, 800 MW. In 2022, it was planned to test the operation of the power part of the excitation system with Emerson Ovation relay protection. The project was suspended due to military operations on the territory of Ukraine

Photo

Development of an independent thyristor excitation system SNVTG-600-200-1.6-UHL4 for the project "Commissioning of a steam turbine installed at power plant No. 3 (TPP–3) in Kharkiv"

Years of implementation2021-2023
Type of works

Design, manufacturing, commissioning of the independent thyristor excitation system SNVTG-600-600-200-1.6-UHL4 (RE LLC "PREOBRAZOVATELNAYA TEHNIKA"), turbogenerator protection cabinets based on ABB REG 670 terminals (with calculation of protection settings), synchronization system based on ABB SYNCHROTACT 6 SYN6201

Equipment used; specifics of works provided

Independent thyristor excitation system SNVTG-600-200-1.6-UHL4 with forced air cooling, turbogenerator protection cabinets based on ABB REG 670 terminals, synchronization system based on ABB SYNCHROTACT 6 SYN6201

Photo

 

Reconstruction of the excitation system of a 25 MW turbine generator (replacement of the VT-120-3000 exciter of a 25 MW turbine generator with a thyristor self-excitation system SSTE-400-300-2.5-UHL4, Mariupol, Leporsky str. 1)

Years of implementation2021-2022
Type of works

Design. Project implementation has been suspended due to military operations in Ukraine

Equipment used; specifics of works provided

Thyristor self-excitation system SSTE-400-300-2.5-UHL4 (LLC "RDE "PREOBRAZOVATEL-COMPLEX")

Photo 